- Preparation and agreement of the transfer’s schedule
- Organization of all necessary equipment (trolleys, cranes, essential personnel)
- Disassembly of machines and preparation for transport (preparation of descriptive documentation facilitating reassembly)
- Transportation to the designated location and reassembly. If necessary: organization of subcontractors necessary for commissioning - ventilation, air conditioning, machine geometry, surveying work, etc.
- Preparation of machines for final acceptance.